St. Luke's Episcopal Health System - Normal Power Project

Project Details:

The Normal Power project consists of removing and replacing existing switch gears, transformers, automatic transfer switches, air handling units, switch boards, and fire sprinkler systems in the mechanical and electrical rooms that are two-stories below the fully occupied hospital. Due to the amount of departments affected, heavy coordination had to be performed with each department manager.

Engagement:

Milestone was engaged as the Owner's Representative / Project Management firm on behalf of St. Luke's Episcopal Health System. MPM oversaw the construction process through the occupancy of the project.

Project Address:

6720 Bertner Avenue
Houston,TX 77030
St. Luke's Episcopal Health System (Non-Profit)

Milestone Personnel:

Eric Serna, Project Manager

Project Team:

Engineer of Record:
Burns DeLatte & McCoy

Architect of Record:
Curry Boureaux

Electrical Contractor:
Fisk Electric

General Contractor:
Millennium Project Solutions

Equipment Vendor:
General Electric