St. Luke's Episcopal Hospital - CT #1 Renovation

Project Details:

The renovation of CT Room #1 was a highly complex project from an hospital operations and construction logistics standpoint. Milestone facilitated a detailed and highly coordinated schedule, allowing the Imaging Department to remain fully functional. The new 128 slice CT was expeditiously installed in a very aesthetically pleasing room on time and under budget.

Engagement:

Milestone was engaged as the Owner's Representative/Project Management firm on behalf of St. Luke's Episcopal Health System. MPM oversaw the construction process through the occupancy of the project.

Project Address:

6720 Bertner Avenue
Houston,TX 77030
St. Luke's Episcopal Health System (Non-Profit)

Milestone Personnel:

Caryn Ogier, Project Manager
Dana Harrison PMP, Assist. Project Manager

Project Team:

Architecture:
PBK Architects

General Contractor:
JE Dunn Construction Company